The Nation · Megaproject · Water

Melamchi Water Supply Project

मेलम्ची खानेपानी आयोजना

Delayed

23 years from approval to first drop of water. 14 years past the original deadline.

Original cost

USD 464.00M

as of 2000

Current cost

USD 700.00M

+51% overrun

Approved

2000-12

Deadline 2007

Delivered

2021-03

14 years late

How we got here

Approved by ADB in December 2000 with a USD 464M envelope and a 2007 delivery target, Melamchi became Nepal's longest-running megaproject failure. The original Italian contractor CMC di Ravenna walked off site in December 2018 citing security and payment disputes, leaving the 26.5km tunnel ~93% complete. China Railway 15 Bureau picked up the work in 2019 and water finally reached Sundarijal on 28 March 2021 — only for the June 2021 Helambu flood to destroy the headworks, suspending supply for over a year. Supply is now seasonal: dry-season only, with monsoon-season shutdowns ongoing.

The short version

Nepal started building a tunnel to bring water to Kathmandu in 2000. It was supposed to be done in 2007. Water finally arrived in 2021 — then a flood broke it three months later. It still only works half the year.

Who paid for it

Asian Development Bank

multilateral

USD 120 million (original); supplementary USD 25M (2010), USD 60M (2017)

Concessional loan

Government of Nepal

domestic

Counterpart funding

JICA / OPEC Fund / Nordic Development Fund

multilateral

Co-financing

Who built it

CMC di Ravenna

Italy · Main tunnel contractor

2013–2018

withdrawn

China Railway 15 Bureau Group

China · Tunnel completion contractor

2019–2021

completed

Implementing authority: Melamchi Water Supply Development Board (MWSDB)

Timeline

  1. 1973

    First feasibility study commissioned

  2. 2000-12

    ADB approves Loan 1820-NEP, USD 120M

    Source: ADB

  3. 2007

    Original delivery target — missed

  4. 2013

    CMC di Ravenna awarded main tunnel contract

  5. 2018-12

    CMC walks off site, tunnel ~93% complete

    Source: MWSDB

  6. 2019-04

    China Railway 15 Bureau awarded completion contract

  7. 2021-03-28

    First water reaches Sundarijal treatment plant

    Source: MWSDB

  8. 2021-06-15

    Helambu flood destroys headworks; supply suspended

    Source: MWSDB

  9. 2022-03

    Dry-season supply resumes

Delivered

Tunnel built. 170 million litres/day delivered to Kathmandu in dry season.

Failed to deliver

Monsoon-season operation. Cost discipline (51% over budget). Schedule (14 years late).

Sources · cited verbatim

  • Asian Development BankMelamchi Water Supply Project — Completion Report (Loan 1820-NEP)

    Open release checked 2024-12-31
  • Office of the Auditor General Nepal (OAGN)Annual Report — Melamchi Water Supply Development Board

    Open release checked 2024-08-15
  • Melamchi Water Supply Development BoardProject chronology and status updates

    Open release checked 2025-01-10

Every value on this page traces back to one of these documents. If you find a discrepancy with the publisher's current dataset, please report it via contact.