Gautam Buddha International Airport, Bhairahawa

गौतम बुद्ध अन्तर्राष्ट्रिय विमानस्थल, भैरहवा

Delivered

USD 95.95M ADB-led build. Opened five years late. Mostly empty.

Original cost

USD 76.00M

as of 2014

Current cost

USD 95.95M

+26% overrun

Approved

2014-04

Deadline 2017

Delivered

2022-05-16

5 years late

How we got here

Pitched as a religious-tourism gateway to Lumbini, GBIA was approved in 2014 with a 2017 target. Construction by Northwest Civil Aviation Airport Construction Group (China) ran five years long; the airport opened on 16 May 2022. As of mid-2026 it operates very limited international traffic, with Jazeera Airways and a handful of regional carriers maintaining intermittent service. The OAGN has flagged the gap between projected and realised traffic in successive annual reports.

The short version

Nepal borrowed USD 87.5 million from ADB and the OPEC Fund to build an international airport near Lumbini. It opened in 2022, five years late. Almost no international flights use it.

Who paid for it

Asian Development Bank

multilateral

USD 76 million

Concessional loan

OPEC Fund for International Development

multilateral

USD 11.5 million (co-financing)

Who built it

Northwest Civil Aviation Airport Construction Group

China · EPC contractor

2015–2022

completed

Implementing authority: Civil Aviation Authority of Nepal (CAAN)

Timeline

  1. 2009

    Project feasibility approved

  2. 2014-04

    ADB Loan 3260-NEP signed (USD 76M)

    Source: ADB

  3. 2015

    Northwest Civil Aviation begins construction

  4. 2017

    Original target completion — missed

  5. 2022-05-16

    Airport opens

    Source: CAAN

  6. 2022-06

    Jazeera Airways begins service from Kuwait

    Source: CAAN

  7. 2024

    OAGN flags low utilisation

    Source: OAGN

Delivered

Airport built, runway and terminal operational, religious-tourism arrivals possible.

Failed to deliver

Volume target. Indian airspace approvals for direct routing not secured at scale. Loan service continues on underutilised asset.

Sources · cited verbatim

  • Asian Development BankGautam Buddha Airport Project — Completion Report (Loan 3260-NEP)

    Open release checked 2024-09-30
  • Civil Aviation Authority of NepalGBIA — Operational status reports

    Open release checked 2024-11-20
  • Office of the Auditor General NepalOAGN Annual Report — CAAN section

    Open release checked 2024-08-15

Every value on this page traces back to one of these documents. If you find a discrepancy with the publisher's current dataset, please report it via contact.